Plastic Omnium chooses APL to upgrade one of its data centers
| Customer name : | Plastic Omnium |
| Area of business : | Manufacturing |
| Accompanying mode : | Turnkey project |
| Type of service : | Improve the reliability of an existing data center - Make upgrades and works without interrupting IT production |
The Auto Exterior division of Plastic Omnium solicited APL to upgrade and improve the reliability of the data center that serves its R&D site. After analyzing the feasibility of upgrading the center from TIER I to TIER III, APL was tasked with executing the entire turn-key project without interrupting IT production.
Project objective
- Upgrade a critical data center so that it meets service continuity requirements for the R&D division
- Evaluate the works and equipment needed in order to reach Tier III, within a restrained budget
- Execute the project in an active data center, without interrupting IT production
Services provided
- Analysis and recommendations for works and equipment needed to reach the expected availability, energy efficiency, and scalability objectives
- Evaluation and detailed management of risks for each operation
- Turn-key execution: creation of two new independent electrical systems, installation of a redundant cooling system, relocation of computer equipment to racks
- Definition of good practices for operating the data center, in order to maintain the expected levels of service continuity and energy efficiency
Client benefits
- State-of-the-art site upgrades, in order to reach Tier III
- Improved data center reliability, with redundant service equipment (electrical and cooling systems)
- Improved cooling system efficiency thanks to the organization and air-flow management used in the room (hot aisle containment)
- No interruption of IT production throughout project execution
- Skills transfer to in-house personnel to operate the computer room in accordance with best practices, in order to achieve the expected levels of service continuity and energy efficiency
Last News
Data centers: an already responsible industry with room for further improvement
Often criticized for their energy and water consumption and their overall environmental impact, data centers remain one of the pillars ...
En savoir plus
APL Data Center CSR review: key achievements and future prospects
APL Data Center has been a signatory to the United Nations Global Compact since 2024. This membership led us to ...
En savoir plus
Third location in Europe: APL Data Center opens a new office in Spain
APL Data Center, the French leader in consulting and engineering specializing in the design and construction of data centers, announces ...
En savoir plus