APL builds a new free-cooling data center for Groupama
| Customer name : | Groupama |
| Area of business : | Insurance |
| Accompanying mode : | Consulting - Project management |
| Type of service : | Assistance with the design and construction of a high energy efficiency data center |
Groupama Systèmes d'Information (GSI), which manages all IT production for the insurance group Groupama, decided to create a data center that would serve as a backup for its old center in Bourges, France, while also hosting a portion of its development IT.
GSI chose APL, which was making upgrades to the old site, to build this new, 3250-m² data center—dubbed "M2"—in the Rennes region.
Project objective
- Build a data center with very high levels of availability
- Anticipate growth in IT demands
- Ensure the energy efficiency of the site
- Adhere to the Flood Risk Prevention Plan and earthquake regulations
Services provided
- Design assistance: dimensioning, comparison of different options for containment and load balancing
- Thermal simulations, to compare different layout scenarios and anticipate fluctuations
- Organization of 4 computer rooms, each with 200 m² of compute space
- Economical and environmental analysis: estimation of energy consumption and PUE, advantages of free-cooling compared to other cooling solutions
Client benefits
- Data center designed and constructed within the prescribed timeframe (18 months)
- An HPE (High Energy Performance) site: high quality energy production, lighting, and free cooling of equipment supported by hydro-cooling units in the room
- Scalable data center architecture and installations, in order to absorb load spikes (with power draws varying between 1.5 kW HQ/m² and 3kW HQ/m²)
- Redundancy of all technical installations (electrical and climate control networks), in order to ensure continuity of service during construction, maintenance, load spikes, etc.
- Economical site performance, with very low operating costs
Last News
APL Data Center announces the entry of CAPZA and ISAI funds into its capital to accelerate its development in Europe and internationally
Paris, April 16, 2026 — APL Data Center, a leading French consulting and engineering firm specializing in the design and ...
En savoir plus
Data Centers Waste Heat: What Are the Requirements Under the DDADUE Law?
France has transposed European Directive 2023/1791 on energy efficiency through the so-called DDADUE law. Data centers are particularly affected, as ...
En savoir plus
White paper: measuring the environmental impact of data centers to take better decisions
APL Data Center and Data4 invite you to download a white paper revealing the complete results of a Life Cycle ...
En savoir plus